The Jefferson County Public Sewer District (JCPSD) proposes to expand the Yorktown Wastewater Treatment Facility to increase its capacity and improve its operational efficiency. The expansion project will involve the addition of a new reinforced concrete tank to the existing facility and the installation of equipment for a sequencing batch reactor (SBR) process. This upgrade will enhance the facility’s ability to treat wastewater and protect the local environment.

Scope of Work:

The project scope includes the following key components:

  • Site Preparation: Excavation of the site for the new tank and associated infrastructure.
  • Concrete Construction: Construction of a new reinforced concrete tank to house the SBR process.
  • Equipment Installation: Installation of wastewater processing equipment, including the SBR system, pumps, piping, valves, and process controls.
  • Piping: Installation of piping systems to connect the new tank and equipment to the existing facility.
  • Electrical Construction: Installation of electrical wiring, conduits, and control panels for the new equipment.
  • Fencing: Construction of fencing to secure the expanded facility.
  • Grading: Final grading of the site to ensure proper drainage and landscaping.

Project Constraints:

  • Existing Facility Operation: The existing wastewater treatment facility must remain operational throughout the construction period with minimal disruptions to service.
  • Environmental Compliance: The project must comply with all applicable environmental regulations and permits.
  • Budget: The project is subject to a defined budget.

DISTRICT CONTACT PERSON:

Offerors shall submit the SOQ to

Douglas Bjornstad, PE, District Director

Jefferson County Public Sewer District

4629 Yeager Road

Hillsboro, MO 63050

dbjornstad@jeffcopsd.org

 

SOQ DUE DATE AND TIME

Offeror’s SOQ shall be submitted to the District Contact Person in electronic, searchable pdf format and six (6) total hard copies, no later than 2:00 p.m. January 31, 2025 on the date listed in Section 2.5 (“SOQ Due Date”).

Please Click HERE for detailed information on submitting a SOQ for the Yorktown Wastewater Treatment Facility Improvement Project.

Please Click HERE for a detailed information packet on submitting a RFQ for the Yorktown Wastewater Treatment Facility Improvement Project.